As a pioneering renewable energy project, Noor Energy 1 is the fourth phase of the Mohammed Bin Rashid Al Maktoum Solar Park, with a total capacity of 950MW. Developed by a consortium led by ACWA Power, DEWA, and Silk Road Fund, it is the largest single-site Concentrated Solar Power (CSP) plant in the world.

By utilizing Central Tower, Parabolic Trough, and Photovoltaic technologies, Noor Energy 1 ensures continuous, round-the-clock power generation, reducing 1.6 million tons of CO₂ emissions annually and providing clean energy to over 320,000 homes.

This project supports the Dubai Clean Energy Strategy 2050, reinforcing the UAE’s commitment to sustainability, energy security, and carbon reduction while setting new benchmarks for renewable energy innovation.

^

Vision

Our vision is to be the world’s leading renewable energy platform, delivering uninterrupted clean power to support Dubai’s transition to sustainable energy. Noor Energy 1 is dedicated to pioneering advanced solar technologies that provide round-the-clock renewable energy, reducing dependence on fossil fuels and contributing to the Dubai Clean Energy Strategy 2050. By setting new benchmarks in innovation, efficiency, and environmental responsibility, we strive to accelerate the global shift toward a carbon-free future while ensuring energy security for generations to come.

Mission

At Noor Energy 1, our mission is to safely develop, operate, and maintain the world’s largest Concentrated Solar Power (CSP) plant while upholding the highest standards of quality, efficiency, and sustainability. With the support of global stakeholders, industry-leading expertise, and a highly skilled team, we are committed to delivering continuous, clean, and cost-effective energy. Our focus is not only on advancing solar power generation but also on minimizing environmental impact, supporting economic growth, and ensuring a resilient, future-ready energy infrastructure. Through innovation, responsibility, and excellence, we are shaping the future of renewable energy and reinforcing Dubai’s position as a leader in sustainable development.

Timeline

December 2018
NTP
January 2020
Completion of the central tower (CT)
June 2020
Molten Salt Receiver (MSR) lifting
November 2020
First Storage Tank Erection Completion
July 2021
Salt Melting Process Begins
November 2021
Heat Transfer Fluid (HTF) Filling
September 2021
Back Energization
March 2022
Molten Salt Receiver (MSR) First Flux
December 2023
Project Inauguration by H.H. Sheikh Mohammed Bin Rashid Al Maktoum